What is the purpose of communication and consultation (6.2)?
Communication & Consultation (6.2)
- To advertise the organization's products to new customers
- To help stakeholders understand risk, the basis for decisions and the reasons actions are required
- To report all incidents to the media immediately
- To advertise the organization's products and report all incidents to the media immediately
Show answer
Answer: B — To help stakeholders understand risk, the basis for decisions and the reasons actions are required
6.2 states the purpose of communication and consultation.
How to solve:- Understanding.
- Basis for decisions.
What does 6.3 "scope, context and criteria" aim to do?
Scope, Context & Criteria (6.3)
- Set the price of insurance for each risk and choose staff for the risk team
- Customize the risk management process to enable effective assessment and treatment
- Approve the final list of all treatments
- Set the price of insurance for each risk
Show answer
Answer: B — Customize the risk management process to enable effective assessment and treatment
6.3.1: purpose of establishing scope, context and criteria.
How to solve:- Customize.
- Effective assessment.
What is the purpose of risk identification (6.4.2)?
Risk Identification & Analysis (6.4.2-6.4.3)
- To choose treatment options for each risk
- To calculate the financial impact of each risk
- To find, recognize and describe risks that might help or prevent achieving objectives
- To calculate the financial impact of each risk and choose treatment options for it
Show answer
Answer: C — To find, recognize and describe risks that might help or prevent achieving objectives
6.4.2 defines the purpose of identification.
How to solve:- Find.
- Describe.
What is the purpose of risk evaluation (6.4.4)?
Risk Evaluation & Treatment (6.4.4-6.5)
- To identify new risks and design controls for each one
- To identify new risks in the organization
- To support decisions by comparing analysis results with risk criteria
- To report losses to shareholders
Show answer
Answer: C — To support decisions by comparing analysis results with risk criteria
6.4.4 describes evaluation.
How to solve:- Compare with criteria.
- Decide.
What is the purpose of monitoring and review (6.6)?
Monitoring, Review, Recording & Reporting (6.6-6.7)
- To assure and improve the quality and effectiveness of process design, implementation and outcomes
- To find staff to blame for risk events
- To find staff to blame for risk events and replace the need for assessment
- To replace the need for risk assessment
Show answer
Answer: A — To assure and improve the quality and effectiveness of process design, implementation and outcomes
6.6 describes monitoring and review.
How to solve:- Quality.
- Effectiveness.
When should communication and consultation take place in the risk process?
Communication & Consultation (6.2)
- Only at the end of the process, after all risk treatments have been put in place
- Only at the end after risk treatment
- Within and throughout all steps of the process
- Only at the start when setting scope
Show answer
Answer: C — Within and throughout all steps of the process
6.2: it should take place within and throughout all steps.
How to solve:- Throughout.
- All steps.
What does defining the scope (6.3.2) involve?
Scope, Context & Criteria (6.3)
- Listing all employees of the organization and designing the office layout
- Defining the scope of risk management activities, objectives and decisions to be made
- Listing all employees of the organization
- Choosing the external auditor
Show answer
Answer: B — Defining the scope of risk management activities, objectives and decisions to be made
6.3.2 explains scope.
How to solve:- Activities.
- Decisions.
Why is relevant, up-to-date information important in identification?
Risk Identification & Analysis (6.4.2-6.4.3)
- It is only needed for audits and slows the identification process down
- It slows the process
- It is only needed for audits
- It helps identify risks accurately
Show answer
Answer: D — It helps identify risks accurately
6.4.2: relevant, appropriate and up-to-date information is important.
How to solve:- Up to date.
- Relevant.
Which decision can result from risk evaluation (6.4.4)?
Risk Evaluation & Treatment (6.4.4-6.5)
- Always transfer the risk to insurers
- Always eliminate the risk completely
- Always eliminate the risk completely, or else stop the activity immediately
- Do nothing further, consider treatment options, undertake further analysis, maintain controls or reconsider objectives
Show answer
Answer: D — Do nothing further, consider treatment options, undertake further analysis, maintain controls or reconsider objectives
6.4.4 lists possible decisions.
How to solve:- Options.
- Reconsider.
When should monitoring and review take place?
Monitoring, Review, Recording & Reporting (6.6-6.7)
- Only once a year at the year end
- Only once a year at the year end, or after a major incident
- Only when the regulator visits
- In all stages of the process, as a planned part of it with defined responsibilities
Show answer
Answer: D — In all stages of the process, as a planned part of it with defined responsibilities
6.6: in all stages, planned, with defined responsibilities.
How to solve:- All stages.
- Planned.
💡 How to practise
- Read each rule (UCP 600, ISBP, URDG, ISP98) article by article and practise the matching chapter.
- Case-scenario questions test how rules work together — review every explanation.
- Take a timed exam to get used to answering under pressure.
- Repeat chapters where you score below 75%.