ISO 31000 (Risk Management Certification) Risk Management Process (Clause 6) – MCQs

Questions across 5 chapters of ISO 31000 (Risk Management Certification) Risk Management Process (Clause 6). Pick a chapter, read sample questions with answers, then take a free test. Available in English.

📚 Chapters

✅ Practice questions with answers

  1. What is the purpose of communication and consultation (6.2)?

    Communication & Consultation (6.2)

    1. To advertise the organization's products to new customers
    2. To help stakeholders understand risk, the basis for decisions and the reasons actions are required
    3. To report all incidents to the media immediately
    4. To advertise the organization's products and report all incidents to the media immediately
    Show answer

    Answer: B — To help stakeholders understand risk, the basis for decisions and the reasons actions are required

    6.2 states the purpose of communication and consultation.

    How to solve:
    • Understanding.
    • Basis for decisions.
  2. What does 6.3 "scope, context and criteria" aim to do?

    Scope, Context & Criteria (6.3)

    1. Set the price of insurance for each risk and choose staff for the risk team
    2. Customize the risk management process to enable effective assessment and treatment
    3. Approve the final list of all treatments
    4. Set the price of insurance for each risk
    Show answer

    Answer: B — Customize the risk management process to enable effective assessment and treatment

    6.3.1: purpose of establishing scope, context and criteria.

    How to solve:
    • Customize.
    • Effective assessment.
  3. What is the purpose of risk identification (6.4.2)?

    Risk Identification & Analysis (6.4.2-6.4.3)

    1. To choose treatment options for each risk
    2. To calculate the financial impact of each risk
    3. To find, recognize and describe risks that might help or prevent achieving objectives
    4. To calculate the financial impact of each risk and choose treatment options for it
    Show answer

    Answer: C — To find, recognize and describe risks that might help or prevent achieving objectives

    6.4.2 defines the purpose of identification.

    How to solve:
    • Find.
    • Describe.
  4. What is the purpose of risk evaluation (6.4.4)?

    Risk Evaluation & Treatment (6.4.4-6.5)

    1. To identify new risks and design controls for each one
    2. To identify new risks in the organization
    3. To support decisions by comparing analysis results with risk criteria
    4. To report losses to shareholders
    Show answer

    Answer: C — To support decisions by comparing analysis results with risk criteria

    6.4.4 describes evaluation.

    How to solve:
    • Compare with criteria.
    • Decide.
  5. What is the purpose of monitoring and review (6.6)?

    Monitoring, Review, Recording & Reporting (6.6-6.7)

    1. To assure and improve the quality and effectiveness of process design, implementation and outcomes
    2. To find staff to blame for risk events
    3. To find staff to blame for risk events and replace the need for assessment
    4. To replace the need for risk assessment
    Show answer

    Answer: A — To assure and improve the quality and effectiveness of process design, implementation and outcomes

    6.6 describes monitoring and review.

    How to solve:
    • Quality.
    • Effectiveness.
  6. When should communication and consultation take place in the risk process?

    Communication & Consultation (6.2)

    1. Only at the end of the process, after all risk treatments have been put in place
    2. Only at the end after risk treatment
    3. Within and throughout all steps of the process
    4. Only at the start when setting scope
    Show answer

    Answer: C — Within and throughout all steps of the process

    6.2: it should take place within and throughout all steps.

    How to solve:
    • Throughout.
    • All steps.
  7. What does defining the scope (6.3.2) involve?

    Scope, Context & Criteria (6.3)

    1. Listing all employees of the organization and designing the office layout
    2. Defining the scope of risk management activities, objectives and decisions to be made
    3. Listing all employees of the organization
    4. Choosing the external auditor
    Show answer

    Answer: B — Defining the scope of risk management activities, objectives and decisions to be made

    6.3.2 explains scope.

    How to solve:
    • Activities.
    • Decisions.
  8. Why is relevant, up-to-date information important in identification?

    Risk Identification & Analysis (6.4.2-6.4.3)

    1. It is only needed for audits and slows the identification process down
    2. It slows the process
    3. It is only needed for audits
    4. It helps identify risks accurately
    Show answer

    Answer: D — It helps identify risks accurately

    6.4.2: relevant, appropriate and up-to-date information is important.

    How to solve:
    • Up to date.
    • Relevant.
  9. Which decision can result from risk evaluation (6.4.4)?

    Risk Evaluation & Treatment (6.4.4-6.5)

    1. Always transfer the risk to insurers
    2. Always eliminate the risk completely
    3. Always eliminate the risk completely, or else stop the activity immediately
    4. Do nothing further, consider treatment options, undertake further analysis, maintain controls or reconsider objectives
    Show answer

    Answer: D — Do nothing further, consider treatment options, undertake further analysis, maintain controls or reconsider objectives

    6.4.4 lists possible decisions.

    How to solve:
    • Options.
    • Reconsider.
  10. When should monitoring and review take place?

    Monitoring, Review, Recording & Reporting (6.6-6.7)

    1. Only once a year at the year end
    2. Only once a year at the year end, or after a major incident
    3. Only when the regulator visits
    4. In all stages of the process, as a planned part of it with defined responsibilities
    Show answer

    Answer: D — In all stages of the process, as a planned part of it with defined responsibilities

    6.6: in all stages, planned, with defined responsibilities.

    How to solve:
    • All stages.
    • Planned.