PMP (Project Management Professional) Process: Planning & Delivery – MCQs
Questions across 8 chapters of PMP (Project Management Professional) Process: Planning & Delivery. Pick a chapter, read sample questions with answers, then take a free test. Available in English.
📚 Chapters
✅ Practice questions with answers
The scope baseline consists of:
Scope & Requirements Management
- the risk register
- the charter only
- the schedule and budget
- the approved scope statement, WBS and WBS dictionary
Show answer
Answer: D — the approved scope statement, WBS and WBS dictionary
Scope baseline.
How to solve:Collect requirements, define scope, create WBS (100% rule, work packages, WBS dictionary). Scope baseline = scope statement + WBS + WBS dictionary. Validate scope = customer acceptance; control quality = correctness. Avoid gold plating and scope creep.
The critical path is:
Schedule Management & Critical Path
- the most expensive path
- the shortest path
- the longest path through the network, determining the shortest project duration
- the path with most resources
Show answer
Answer: C — the longest path through the network, determining the shortest project duration
Critical path.
How to solve:Precedence diagramming (FS, SS, FF, SF). Critical path = longest path, zero total float. Float = LS - ES or LF - EF. PERT (beta) = (O + 4M + P)/6, SD = (P - O)/6. Compression: crashing (add resources, more cost) and fast tracking (overlap, more risk).
Earned value (EV) is:
Cost Management & Earned Value
- the planned value
- the value of work actually completed, measured in budget terms
- the actual cost spent
- the total budget
Show answer
Answer: B — the value of work actually completed, measured in budget terms
EV.
How to solve:EV = % complete x BAC. CV = EV - AC; SV = EV - PV; CPI = EV/AC; SPI = EV/PV. EAC = BAC/CPI (typical); EAC = AC + (BAC - EV) (atypical). ETC = EAC - AC. VAC = BAC - EAC. TCPI = (BAC - EV)/(BAC - AC).
Quality is:
- the degree to which a set of inherent characteristics fulfils requirements
- the number of features
- the same as grade
- the price of a product
Show answer
Answer: A — the degree to which a set of inherent characteristics fulfils requirements
Quality.
How to solve:Quality = degree to which characteristics fulfil requirements; grade = category. Cost of quality: conformance (prevention, appraisal) vs nonconformance (internal, external failure). Manage quality (process, audits) vs control quality (inspect deliverables). Control chart rule of seven. Deming PDCA.
In a firm fixed price (FFP) contract, cost risk is mainly borne by:
- the buyer
- equally by both
- the sponsor
- the seller
Show answer
Answer: D — the seller
FFP.
How to solve:Contract types: fixed price (FFP, FPIF, FP-EPA) – seller risk; cost-reimbursable (CPFF, CPIF, CPAF) – buyer risk; T&M – hybrid. Make-or-buy analysis. Bidder conferences. PTA = ((Ceiling price - Target price)/Buyer's share) + Target cost.
A risk is:
- only a negative event
- a problem that has occurred
- an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives
- a certain event
Show answer
Answer: C — an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives
PMI definition.
How to solve:Risk = uncertain event that may affect objectives (threat or opportunity). Threat responses: escalate, avoid, transfer, mitigate, accept. Opportunity responses: escalate, exploit, share, enhance, accept. EMV = probability x impact. Risk register, risk owner, contingency/fallback plans, residual and secondary risks.
The project management plan:
- is only the budget
- integrates subsidiary plans and baselines and describes how the project will be executed, monitored and closed
- is the same as the schedule
- is the charter
Show answer
Answer: B — integrates subsidiary plans and baselines and describes how the project will be executed, monitored and closed
PM plan.
How to solve:Integrated change control: changes are documented in a change request, analysed for impact on scope, time, cost, quality and risk, approved or rejected by the CCB, then plans and baselines are updated and stakeholders informed. Project management plan integrates all subsidiary plans and baselines.
The first activity in closing a project is usually to:
Project Closure & Lessons Learned
- confirm that all deliverables have been formally accepted
- celebrate
- release the team
- archive files
Show answer
Answer: A — confirm that all deliverables have been formally accepted
Acceptance first.
How to solve:Close project or phase: confirm acceptance, transfer deliverables, close contracts, release resources, archive records, record lessons learned, produce final report. Lessons learned register is updated throughout, not just at the end. Benefits may be realised after closure.
The WBS is:
Scope & Requirements Management
- a cost estimate
- a schedule network
- a hierarchical decomposition of the total scope of work into deliverables
- a list of team members
Show answer
Answer: C — a hierarchical decomposition of the total scope of work into deliverables
WBS.
How to solve:Collect requirements, define scope, create WBS (100% rule, work packages, WBS dictionary). Scope baseline = scope statement + WBS + WBS dictionary. Validate scope = customer acceptance; control quality = correctness. Avoid gold plating and scope creep.
Activities on the critical path normally have:
Schedule Management & Critical Path
- free float of 10 days
- zero total float
- maximum float
- negative cost
Show answer
Answer: B — zero total float
Float.
How to solve:Precedence diagramming (FS, SS, FF, SF). Critical path = longest path, zero total float. Float = LS - ES or LF - EF. PERT (beta) = (O + 4M + P)/6, SD = (P - O)/6. Compression: crashing (add resources, more cost) and fast tracking (overlap, more risk).
💡 How to practise
- Read each rule (UCP 600, ISBP, URDG, ISP98) article by article and practise the matching chapter.
- Case-scenario questions test how rules work together — review every explanation.
- Take a timed exam to get used to answering under pressure.
- Repeat chapters where you score below 75%.