PRINCE2 Foundation PRINCE2 Overview, Principles & People – MCQs
Questions across 7 chapters of PRINCE2 Foundation PRINCE2 Overview, Principles & People. Pick a chapter, read sample questions with answers, then take a free test. Available in English.
📚 Chapters
✅ Practice questions with answers
PRINCE2 stands for:
PRINCE2 Overview & Project Context
- PRocess INtegration and Control Environment
- Project Resources IN Corporate Enterprises
- PRojects IN Controlled Environments
- Planning and Reporting IN Controlled Environments
Show answer
Answer: C — PRojects IN Controlled Environments
Acronym.
How to solve:PRINCE2 7 (2023) has five integrated elements: principles, people, practices, processes and project context. 7 principles, 7 practices, 7 processes. Seven performance targets: time, cost, quality, scope, benefits, risk and sustainability. Foundation: 60 questions, 60 min, closed book, 60% pass. Practitioner: 70 questions, 150 min, open book, 60% pass.
How many principles does PRINCE2 have?
- ten
- seven
- five
- twelve
Show answer
Answer: B — seven
7 principles.
How to solve:Principles: ensure continued business justification; learn from experience; define roles, responsibilities and relationships; manage by stages; manage by exception; focus on products; tailor to suit the project. All must be applied for a project to be PRINCE2.
The three primary project interests in PRINCE2 are:
People & the Organizing Practice
- business, user and supplier
- plan, do and check
- finance, HR and IT
- time, cost and quality
Show answer
Answer: A — business, user and supplier
Three interests.
How to solve:Three interests: business (executive), user (senior user), supplier (senior supplier) on the project board. Executive is ultimately accountable and owns the business case. Project assurance is independent of the PM. Change authority, project support, team manager, project manager.
In PRINCE2, an output is:
Business Case Practice & Benefits
- a measurable improvement
- a result of change
- a negative consequence
- a specialist product handed over to a user
Show answer
Answer: D — a specialist product handed over to a user
Output.
How to solve:Outputs (products) lead to outcomes (results of change) which lead to benefits (measurable improvements). Dis-benefits are negative outcomes. Business case: developed in SU (outline), refined in IP, updated at stage boundaries, reviewed at closure. Benefits management approach covers post-project reviews.
The levels of plan recommended by PRINCE2 are:
Plans Practice & Product-Based Planning
- portfolio plan only
- only one master plan
- project plan, stage plans and team plans, with exception plans as needed
- daily plans only
Show answer
Answer: C — project plan, stage plans and team plans, with exception plans as needed
Plan levels.
How to solve:Plan levels: project plan (project board), stage plan (PM), team plan (team manager, optional), exception plan (replaces the plan in exception). Product-based planning: write project product description, create product breakdown structure, write product descriptions, create product flow diagram.
Customer's quality expectations are:
- the budget limit
- statements about the quality expected from the project product, captured in the project product description
- the PM's opinion
- the supplier's internal standards only
Show answer
Answer: B — statements about the quality expected from the project product, captured in the project product description
Quality expectations.
How to solve:Customer's quality expectations and acceptance criteria are captured in the project product description. Quality management approach, product descriptions with quality criteria, quality register. Quality planning vs quality control vs quality assurance. Quality review technique roles: chair, presenter, reviewer, administrator.
A risk is:
- an uncertain event or set of events that, should it occur, will affect the achievement of objectives
- a problem that has happened
- a certain event
- always negative
Show answer
Answer: A — an uncertain event or set of events that, should it occur, will affect the achievement of objectives
PRINCE2 definition.
How to solve:Risk = uncertain event that would affect objectives (threat or opportunity). Risk management procedure: identify, assess, plan, implement, communicate. Cause - event - effect. Risk owner vs risk actionee. Risk appetite and risk tolerance. Responses for threats include avoid, reduce, transfer, share, accept; for opportunities exploit, enhance, share, reject.
The current edition of PRINCE2 (published 2023) is:
PRINCE2 Overview & Project Context
- PRINCE2 2009
- PRINCE2 7th edition
- PRINCE2 2017 (6th edition)
- PRINCE2 2026
Show answer
Answer: B — PRINCE2 7th edition
PRINCE2 7.
How to solve:PRINCE2 7 (2023) has five integrated elements: principles, people, practices, processes and project context. 7 principles, 7 practices, 7 processes. Seven performance targets: time, cost, quality, scope, benefits, risk and sustainability. Foundation: 60 questions, 60 min, closed book, 60% pass. Practitioner: 70 questions, 150 min, open book, 60% pass.
Which is a PRINCE2 principle?
- ensure continued business justification
- always follow every process fully
- deliver with no documentation
- focus on the budget
Show answer
Answer: A — ensure continued business justification
Principle 1.
How to solve:Principles: ensure continued business justification; learn from experience; define roles, responsibilities and relationships; manage by stages; manage by exception; focus on products; tailor to suit the project. All must be applied for a project to be PRINCE2.
The project board consists of:
People & the Organizing Practice
- only suppliers
- the PM, team managers and support
- only the executive
- the executive, senior user(s) and senior supplier(s)
Show answer
Answer: D — the executive, senior user(s) and senior supplier(s)
Project board.
How to solve:Three interests: business (executive), user (senior user), supplier (senior supplier) on the project board. Executive is ultimately accountable and owns the business case. Project assurance is independent of the PM. Change authority, project support, team manager, project manager.
💡 How to practise
- Read each rule (UCP 600, ISBP, URDG, ISP98) article by article and practise the matching chapter.
- Case-scenario questions test how rules work together — review every explanation.
- Take a timed exam to get used to answering under pressure.
- Repeat chapters where you score below 75%.