  1. The three types of issue in PRINCE2 are:

    Issues Practice & Change Control

    1. risk, opportunity, threat
    2. time, cost, quality
    3. plan, report, log
    4. request for change, off-specification, and problem/concern
    Show answer

    Answer: D โ€” request for change, off-specification, and problem/concern

    Issue types.

    How to solve:

    Issue types: request for change, off-specification, problem/concern. Issue management procedure: capture, assess, recommend, decide, implement. Baseline products are changed only through change control. Change authority and change budget. Configuration management keeps product versions under control.

  2. Tolerance is:

    Progress Practice & Tolerances

    1. the project duration
    2. a type of risk
    3. the permissible deviation above and below a plan's target before escalation is needed
    4. the total budget
    Show answer

    Answer: C โ€” the permissible deviation above and below a plan's target before escalation is needed

    Tolerance.

    How to solve:

    Tolerances: business layer sets project tolerances, project board sets stage tolerances, PM sets work package tolerances. Controls: event-driven (stage end, exception) and time-driven (highlight reports from PM to board, checkpoint reports from team manager to PM). Exceptions escalate one level up.

  3. A request for change is:

    Issues Practice & Change Control

    1. a benefit
    2. a product that does not meet its specification
    3. a proposal for a change to a baseline
    4. a risk
    Show answer

    Answer: C โ€” a proposal for a change to a baseline

    Request for change.

    How to solve:

    Issue types: request for change, off-specification, problem/concern. Issue management procedure: capture, assess, recommend, decide, implement. Baseline products are changed only through change control. Change authority and change budget. Configuration management keeps product versions under control.

  4. Project-level tolerances are set by:

    Progress Practice & Tolerances

    1. the team manager
    2. the business layer (corporate, programme or customer)
    3. the project board
    4. the PM
    Show answer

    Answer: B โ€” the business layer (corporate, programme or customer)

    Project tolerance.

    How to solve:

    Tolerances: business layer sets project tolerances, project board sets stage tolerances, PM sets work package tolerances. Controls: event-driven (stage end, exception) and time-driven (highlight reports from PM to board, checkpoint reports from team manager to PM). Exceptions escalate one level up.

  5. An off-specification is:

    Issues Practice & Change Control

    1. a request for a new feature
    2. something that should be provided but is not, or does not meet its specification
    3. a stage plan
    4. a risk
    Show answer

    Answer: B โ€” something that should be provided but is not, or does not meet its specification

    Off-specification.

    How to solve:

    Issue types: request for change, off-specification, problem/concern. Issue management procedure: capture, assess, recommend, decide, implement. Baseline products are changed only through change control. Change authority and change budget. Configuration management keeps product versions under control.

  6. Stage-level tolerances are set by:

    Progress Practice & Tolerances

    1. the project board
    2. the business layer
    3. the PM
    4. the team manager
    Show answer

    Answer: A โ€” the project board

    Stage tolerance.

    How to solve:

    Tolerances: business layer sets project tolerances, project board sets stage tolerances, PM sets work package tolerances. Controls: event-driven (stage end, exception) and time-driven (highlight reports from PM to board, checkpoint reports from team manager to PM). Exceptions escalate one level up.

  7. A problem/concern is:

    Issues Practice & Change Control

    1. any other issue the PM needs to resolve or escalate
    2. a benefit
    3. an off-specification
    4. a change request
    Show answer

    Answer: A โ€” any other issue the PM needs to resolve or escalate

    Problem/concern.

    How to solve:

    Issue types: request for change, off-specification, problem/concern. Issue management procedure: capture, assess, recommend, decide, implement. Baseline products are changed only through change control. Change authority and change budget. Configuration management keeps product versions under control.

  8. Work package tolerances are set by:

    Progress Practice & Tolerances

    1. the project board
    2. the senior user alone
    3. the business layer
    4. the project manager
    Show answer

    Answer: D โ€” the project manager

    WP tolerance.

    How to solve:

    Tolerances: business layer sets project tolerances, project board sets stage tolerances, PM sets work package tolerances. Controls: event-driven (stage end, exception) and time-driven (highlight reports from PM to board, checkpoint reports from team manager to PM). Exceptions escalate one level up.

  9. The issue management procedure steps are:

    Issues Practice & Change Control

    1. identify, assess, plan, implement, communicate
    2. plan, do, check, act
    3. start, run, close
    4. capture, assess, recommend, decide and implement
    Show answer

    Answer: D โ€” capture, assess, recommend, decide and implement

    Issue procedure.

    How to solve:

    Issue types: request for change, off-specification, problem/concern. Issue management procedure: capture, assess, recommend, decide, implement. Baseline products are changed only through change control. Change authority and change budget. Configuration management keeps product versions under control.

  10. If a work package is forecast to exceed its tolerances, the team manager should:

    Progress Practice & Tolerances

    1. inform the project board directly
    2. ignore it
    3. raise an issue to the project manager
    4. stop the project
    Show answer

    Answer: C โ€” raise an issue to the project manager

    Escalate one level.

    How to solve:

    Tolerances: business layer sets project tolerances, project board sets stage tolerances, PM sets work package tolerances. Controls: event-driven (stage end, exception) and time-driven (highlight reports from PM to board, checkpoint reports from team manager to PM). Exceptions escalate one level up.

๐Ÿ’ก How to practise