Adarsh Practice

PRINCE2 Foundation PRINCE2 Processes – MCQs

Questions across 7 chapters of PRINCE2 Foundation PRINCE2 Processes. Pick a chapter, read sample questions with answers, then take a free test. Available in English.

📚 Chapters

✅ Practice questions with answers

  1. The trigger for starting up a project is:

    Starting Up a Project (SU)

    1. the end stage report
    2. the project mandate from the business layer
    3. the PID
    4. the exception report
    Show answer

    Answer: B — the project mandate from the business layer

    Mandate.

    How to solve:

    SU is pre-project. It begins with the project mandate from the business layer. Activities: appoint the executive and project manager; capture previous lessons; appoint the project management team; prepare the outline business case; select the project approach and assemble the project brief; plan the initiation stage. Purpose: is the project viable and worthwhile?

  2. Directing a project is the responsibility of:

    Directing a Project (DP)

    1. the project board
    2. project support
    3. the project manager
    4. the team manager
    Show answer

    Answer: A — the project board

    DP.

    How to solve:

    DP is the project board's process, from end of SU to project closure. Activities: authorise initiation; authorise the project; authorise a stage or exception plan; give ad hoc direction; authorise project closure. The board manages by exception.

  3. The purpose of initiating a project is to:

    Initiating a Project (IP)

    1. start SU
    2. close the project
    3. deliver all products
    4. establish solid foundations so the organisation understands the work before committing to a significant spend
    Show answer

    Answer: D — establish solid foundations so the organisation understands the work before committing to a significant spend

    IP purpose.

    How to solve:

    IP is the first management stage. Activities: agree tailoring requirements; prepare the management approaches (risk, issue, quality, communication, benefits, plus digital and data, commercial, sustainability); set up project controls; create the project plan; refine the business case; assemble the PID.

  4. Controlling a stage is mainly performed by:

    Controlling a Stage (CS)

    1. the business layer
    2. the project board
    3. the project manager
    4. the team manager
    Show answer

    Answer: C — the project manager

    CS.

    How to solve:

    CS is the PM's day-to-day process. Activities: authorise a work package; review work package status; receive completed work packages; review the stage status; report highlights; capture and assess issues and risks; escalate issues and risks; take corrective action.

  5. Managing product delivery is mainly performed by:

    Managing Product Delivery (MP)

    1. the business layer
    2. the team manager
    3. the project board
    4. the project manager
    Show answer

    Answer: B — the team manager

    MP.

    How to solve:

    MP is the team manager's process controlling the link between PM and specialist teams. Activities: accept a work package; execute a work package; deliver a work package. Team manager produces checkpoint reports, maintains team plans and ensures quality checks.

  6. Managing a stage boundary is performed by:

    Managing a Stage Boundary (SB)

    1. the project manager
    2. the business layer
    3. the project board
    4. the team manager
    Show answer

    Answer: A — the project manager

    SB.

    How to solve:

    SB occurs near the end of each stage (except the final stage) and when an exception plan is needed. Activities: plan the next stage; update the project plan; update the business case; report stage end; produce an exception plan. Outputs go to the board for authorisation.

  7. Closing a project is performed by:

    Closing a Project (CP)

    1. the senior supplier alone
    2. the team manager
    3. the business layer
    4. the project manager
    Show answer

    Answer: D — the project manager

    CP.

    How to solve:

    CP: prepare planned closure; prepare premature closure; hand over products; evaluate the project; recommend project closure. Outputs: end project report, lessons report, updated benefits management approach, handover acceptance. Board then authorises closure.

  8. The purpose of starting up a project is to:

    Starting Up a Project (SU)

    1. ensure the prerequisites for initiating are in place by answering whether the project is viable and worthwhile
    2. close the project
    3. deliver products
    4. produce work packages
    Show answer

    Answer: A — ensure the prerequisites for initiating are in place by answering whether the project is viable and worthwhile

    SU purpose.

    How to solve:

    SU is pre-project. It begins with the project mandate from the business layer. Activities: appoint the executive and project manager; capture previous lessons; appoint the project management team; prepare the outline business case; select the project approach and assemble the project brief; plan the initiation stage. Purpose: is the project viable and worthwhile?

  9. Directing a project starts:

    Directing a Project (DP)

    1. after closure
    2. during managing product delivery only
    3. at the mandate
    4. after starting up a project, on the request to initiate
    Show answer

    Answer: D — after starting up a project, on the request to initiate

    DP start.

    How to solve:

    DP is the project board's process, from end of SU to project closure. Activities: authorise initiation; authorise the project; authorise a stage or exception plan; give ad hoc direction; authorise project closure. The board manages by exception.

  10. The main output of initiating a project is:

    Initiating a Project (IP)

    1. the project brief
    2. the end project report
    3. the project initiation documentation (PID)
    4. the mandate
    Show answer

    Answer: C — the project initiation documentation (PID)

    PID.

    How to solve:

    IP is the first management stage. Activities: agree tailoring requirements; prepare the management approaches (risk, issue, quality, communication, benefits, plus digital and data, commercial, sustainability); set up project controls; create the project plan; refine the business case; assemble the PID.

💡 How to practise