The trigger for starting up a project is:
- the end stage report
- the project mandate from the business layer
- the PID
- the exception report
Show answer
Answer: B — the project mandate from the business layer
Mandate.
How to solve:SU is pre-project. It begins with the project mandate from the business layer. Activities: appoint the executive and project manager; capture previous lessons; appoint the project management team; prepare the outline business case; select the project approach and assemble the project brief; plan the initiation stage. Purpose: is the project viable and worthwhile?
Directing a project is the responsibility of:
- the project board
- project support
- the project manager
- the team manager
Show answer
Answer: A — the project board
DP.
How to solve:DP is the project board's process, from end of SU to project closure. Activities: authorise initiation; authorise the project; authorise a stage or exception plan; give ad hoc direction; authorise project closure. The board manages by exception.
The purpose of initiating a project is to:
- start SU
- close the project
- deliver all products
- establish solid foundations so the organisation understands the work before committing to a significant spend
Show answer
Answer: D — establish solid foundations so the organisation understands the work before committing to a significant spend
IP purpose.
How to solve:IP is the first management stage. Activities: agree tailoring requirements; prepare the management approaches (risk, issue, quality, communication, benefits, plus digital and data, commercial, sustainability); set up project controls; create the project plan; refine the business case; assemble the PID.
Controlling a stage is mainly performed by:
- the business layer
- the project board
- the project manager
- the team manager
Show answer
Answer: C — the project manager
CS.
How to solve:CS is the PM's day-to-day process. Activities: authorise a work package; review work package status; receive completed work packages; review the stage status; report highlights; capture and assess issues and risks; escalate issues and risks; take corrective action.
Managing product delivery is mainly performed by:
Managing Product Delivery (MP)
- the business layer
- the team manager
- the project board
- the project manager
Show answer
Answer: B — the team manager
MP.
How to solve:MP is the team manager's process controlling the link between PM and specialist teams. Activities: accept a work package; execute a work package; deliver a work package. Team manager produces checkpoint reports, maintains team plans and ensures quality checks.
Managing a stage boundary is performed by:
Managing a Stage Boundary (SB)
- the project manager
- the business layer
- the project board
- the team manager
Show answer
Answer: A — the project manager
SB.
How to solve:SB occurs near the end of each stage (except the final stage) and when an exception plan is needed. Activities: plan the next stage; update the project plan; update the business case; report stage end; produce an exception plan. Outputs go to the board for authorisation.
Closing a project is performed by:
- the senior supplier alone
- the team manager
- the business layer
- the project manager
Show answer
Answer: D — the project manager
CP.
How to solve:CP: prepare planned closure; prepare premature closure; hand over products; evaluate the project; recommend project closure. Outputs: end project report, lessons report, updated benefits management approach, handover acceptance. Board then authorises closure.
The purpose of starting up a project is to:
- ensure the prerequisites for initiating are in place by answering whether the project is viable and worthwhile
- close the project
- deliver products
- produce work packages
Show answer
Answer: A — ensure the prerequisites for initiating are in place by answering whether the project is viable and worthwhile
SU purpose.
How to solve:SU is pre-project. It begins with the project mandate from the business layer. Activities: appoint the executive and project manager; capture previous lessons; appoint the project management team; prepare the outline business case; select the project approach and assemble the project brief; plan the initiation stage. Purpose: is the project viable and worthwhile?
Directing a project starts:
- after closure
- during managing product delivery only
- at the mandate
- after starting up a project, on the request to initiate
Show answer
Answer: D — after starting up a project, on the request to initiate
DP start.
How to solve:DP is the project board's process, from end of SU to project closure. Activities: authorise initiation; authorise the project; authorise a stage or exception plan; give ad hoc direction; authorise project closure. The board manages by exception.
The main output of initiating a project is:
- the project brief
- the end project report
- the project initiation documentation (PID)
- the mandate
Show answer
Answer: C — the project initiation documentation (PID)
PID.
How to solve:IP is the first management stage. Activities: agree tailoring requirements; prepare the management approaches (risk, issue, quality, communication, benefits, plus digital and data, commercial, sustainability); set up project controls; create the project plan; refine the business case; assemble the PID.
💡 How to practise
- Read each rule (UCP 600, ISBP, URDG, ISP98) article by article and practise the matching chapter.
- Case-scenario questions test how rules work together — review every explanation.
- Take a timed exam to get used to answering under pressure.
- Repeat chapters where you score below 75%.